Fostering transparency: Improvement of contractor selection criteria and practices

Authors

  • Muhammad Arman Alias Faculty Industrial Management, Universiti Malaysia Pahang Al-Sultan Abdullah, Lebuh Persiaran Tun Khalil Yaakob, 26300 Kuantan, Pahang, Malaysia
  • Fazeeda Mohamad Faculty Industrial Management, Universiti Malaysia Pahang Al-Sultan Abdullah, Lebuh Persiaran Tun Khalil Yaakob, 26300 Kuantan, Pahang, Malaysia https://orcid.org/0000-0002-2257-8415 (unauthenticated)

DOI:

https://doi.org/10.15282/jgi.8.2.2025.11519

Keywords:

Transparency, Governance, Contractor Selection, Criteria Theory of Constraints, Project Management

Abstract

Most plant maintenance projects (PMP) in chemical manufacturing companies worldwide rarely meet expectations or achieve their objectives. More than 80% of these projects face cost and time overruns. A key contributing factor is poor decision-making in contractor selection (CS) during the contractual phase of the project life cycle. It is therefore critical to select contractors with proven capability to deliver high-quality services in order to achieve better project outcomes. The objective of this paper is to identify the major contractor performance issues that contribute to project delays in PMP and to propose a framework for CS that can enhance project outcomes in chemical manufacturing companies. Contractor underperformance highlights the need for clear and acceptable selection standards during CS activities. This paper addresses existing deficiencies in contractor evaluation by identifying key performance areas and proposing improved methods for selecting contractors who can reduce long-term risks of delays and inefficiencies. Organisations can benefit from this framework by improving service delivery, promoting good governance, and demonstrating how transparency and accountability reduce corruption while ensuring projects achieve their intended outcomes. Effective CS also strengthens compliance with laws, rules, and regulations while enabling risk management that supports efficient operations and maximises business value.

References

Abbasianjahromi, H., Sepehri, M., & Abbasi, O. (2018). A decision-making framework for subcontractor selection in construction projects. EMJ - Engineering Management Journal, 30(2), 141–152.

Abd Wahab, Z., & Shavarebi, K. Enhancing Company Financial Transparency for Contractor Selection Process through XBRL: A Conceptual Framework. Asian Journal of Interdisciplinary Research, 22(33), 22.

Afsath, K., & Sebastian, L. (2015). Fuzzy MATLAB approach to construction contractor selection. International Journal of Scientific Engineering and Research, 4(8), 45-49.

Ahadi, R. H., Alaei, S., & Amini, S., (2017). Developing a framework for prioritizing and selection of civil projects contractors at Tehran municipality. International Journal of Railway Research, 4(1), 29 - 35

Ajayi, B. O., & Chinda, T. (2022). Impact of construction delay-controlling parameters on project schedule: DEMATEL-system dynamics modeling approach. Frontiers in Built Environment, 8, 799314.

Akuffo, I. N., & Kivipõld, K. (2020). Influence of leaders’ authentic competences on nepotism-favouritism and cronyism. Management Research Review, 43(4), 369–386.

Alhumaidi, H. M. (2015). Construction contractors ranking method using multiple decision-makers and multiattribute fuzzy weighted average. Journal of Construction Engineering and Management, 141(4), 04014092.

Aljamee, H., Naeem, S., & Bell, A. (2020). The causes of project delay in Iraqi petroleum industry: a case study in Basra oil company. Journal of Transnational Management, 25(1), 57–70.

Araújo, M. C. B., Alencar, L. H., & Mota, C. M. (2015, December). Contractor selection in construction industry: A multicriteria model. In 2015 IEEE International Conference on Industrial Engineering and Engineering Management (IEEM) (pp. 519-523). IEEE.

Bajjou, M. S., & Chafi, A. (2020). Empirical study of schedule delay in moroccan construction projects. International Journal of Construction Management, 20(7), 783–800.

Baumeister, D., Boes, L., & Laußmann, C. (2022). Time constrained participatory budgeting under uncertain project costs. In Proceedings of the Thirty First International Joint Conference on Artificial Intelligence (IJCAI 2022) (pp. 74–80).

Behboud, R., Zarei, A., Azar, A., & Ebrahimi, S. A. (2023). Failure to develop the world’s largest natural gas field: Lessons from endeavors in the South Pars mega projects. Energy, 272, 127091.

Besson, M., Jacquinot, P., Jardat, R., & Moriceau, J. L. (2023). Escaping transparent, asymmetrical and agentive accountability? Entrepreneurial accounts and researchers' countertransference. Accounting, Auditing & Accountability Journal, 36(7/8), 1790-1813.

Bintoro, I., & Malani, R. (2017, October). Modelling of contractor selection using fuzzy-TOPSIS. In 2017 5Th International Conference on Electrical, Electronics and Information Engineering (ICEEIE) (pp. 140-145). IEEE.

Blonde, L., Khunti, K., Harris, S. B., Meizinger, C., & Skolnik, N. S. (2018). Interpretation and impact of real-world clinical data for the practicing clinician. Advances in Therapy, 35(11), 1763-1774.

Bohari, A. A. M., Ikau, R. A., Budin, H., Hadi, N. A., & Chan, V. S. L. (2021). The key criteria in deciding to tender for construction projects. International Journal of Integrated Engineering, 13(3), 229–235.

Cheaitou, A., Larbi, R., & Al Housani, B. (2019). Decision making framework for tender evaluation and contractor selection in public organizations with risk considerations. Socio-Economic Planning Sciences, 68, 100620.

Chen, W., Yang, Z., Yan, H., & Zhao, Y. (2023). Promoting construction labor professionalization: an evolutionary game perspective. Sustainability, 15(12), 9688.

Chen, Z. S., Zhang, X., Rodríguez, R. M., Pedrycz, W., & Martínez, L. (2021). Expertise-based bid evaluation for construction-contractor selection with generalized comparative linguistic ELECTRE III. Automation in Construction, 125, 103578.

Durdyev, S., & Hosseini, M. R. (2020). Causes of delays on construction projects: a comprehensive list. International journal of managing projects in business, 13(1), 20-46.

Effendi, A. (2019). Selection of IPM geothermal drilling contractor through a merit point system using the Analytical Hierarchy Process. Ekspektra: Jurnal Bisnis dan Manajemen, 3(2), 102–110.

El-Sawalhi, N., & Hajar, Y. A. (2016). Development of awarding system for construction contractors in gaza strip Using Artificial Neural Network (ANN). Journal of Construction Engineering and Project Management, 6(3), 1–7.

Eragamreddy, Dr. N. (2024). Semiotic functions of indexicality. International Journal of Current Science Research and Review, 7(5), 2453-2467.

Ershadi, M., Jefferies, M., Davis, P., & Mojtahedi, M. (2023). Modeling the capabilities of high-performing project management offices in general contracting companies. Project Management Journal, 54(3), 268–284.

Evarist, C., Luvara, V. G. M., & Chileshe, N. (2023). Perception on constraining factors impacting recruitment and selection practices of building contractors in Dar Es Salaam, Tanzania. International Journal of Construction Management, 23(12), 2012–2023.

Fertilizer Industrial Services Ltd. (2018). Turnaround management methodology for fertilizer plants. Retrieved from https://www.ammoniaknowhow.com/doc/turnaround-management-methodology-forfertilizer-plants-document-guidance.pdf

Fong, P. S. W., & Choi, S. K. Y. (2000). Final contractor selection using the analytical hierarchy process. Construction Management and Economics, 18(5), 547–557.

Gharedaghi, G., & Omidvari, M. (2017). A contractor selection model for gas and oil industries in safety approach using ANP-DEMATEL in grey environment. Safety and Reliability, 37(1), 25–47.

Gimhan, A., Zainudeen, N., & Pandithawatta, S. (2019). SWOT analysis for large scale contractors of Sri Lanka. In 2019 Moratuwa Engineering Research Conference (MERCon) (pp. 163-168). IEEE.

Gunasekara, K., Perera, S., Hardie, M., & Jin, X. (2021). A contractor-centric construction performance model using non-price measures. Buildings, 11(8), 375.

Hadidi, L. A., & Khater, M. A. (2015). Loss prevention in turnaround maintenance projects by selecting contractors based on safety criteria using the analytic hierarchy process (AHP). Journal of Loss Prevention in the Process Industries, 34, 115–126.

Hajek, J., Vrbova, L., & Kolis, K. (2017). Hierarchical structure of criteria used for contractor selection for construction works. Empirical research from the Czech Republic. International Journal of Procurement Management, 10(4), 444-460.

Heravi, G., Fathi, M., & Faeghi, S. (2017). Multi-criteria group decision-making method for optimal selection of sustainable industrial building options focused on petrochemical projects. Journal of Cleaner Production, 142, 2999–3013.

Hoseinpoor, A., & Alborzi, M. (2019). The combination of DEA and AHP approach in the selection of contractors participating in tenders. HOLOS, 2, 1–15.

Ibadov, N. (2015). Contractor selection for construction project, with the use of fuzzy preference relation. Procedia Engineering, 111, 317–323.

Ighravwe, D. E., & Oke, S. A. (2019). An integrated approach of SWARA and fuzzy COPRAS for maintenance technicians’ selection factors ranking. International Journal of System Assurance Engineering and Management, 10(6), 1615–1626.

Israel, B. (2023). The impact of clients’ procurement challenges on the substance goals of roads construction projects in Songwe, Tanzania. International Journal of Construction Management, 23(12), 2144–2150.

Jeyaseelan, K., & Sathyamurthi, K. (2023). Business Demand-Oriented Skilling. Online Submission, 5(4), 1-7.

Kamau, N., Gesimba, P., & Gumboh, J. (2022). Determining the effect of sub-contractor’s expertise on service delivery in public hospitals in Nakuru County. Journal of Business and Entrepreneurship (JBE), 1(1), 8–16.

Khoso, A. R., Yusof, A. M., Chen, Z. S., Skibniewski, M. J., Chin, K. S., Khahro, S. H., & Sohu, S. (2022). Comprehensive analysis of state of the art contractor selection models in construction environment: A critical review and future call. Socio Economic Planning Sciences, 79, 101151.

Kim, J., Lim, J., Lim, H. C., & Kim, D. Y. (2022). Improving sustainable project success strategies focused on cost and schedule for electrical construction project management. Sustainability, 14(5), 2964.

Kog, F., & Yaman, H. (2016). A multi-agent systems-based contractor pre-qualification model. Engineering, Construction and Architectural Management, 23(6), 709–726.

Koopman, K., & Cumberlege, R. (2021, February). Cash flow management by contractors. In IOP Conference Series: Earth and Environmental Science (Vol. 654, No. 1, p. 012028). IOP Publishing.

Krzemiński, M. (2015). The selection of construction sub-contractors using the fuzzy sets theory. AIP Conference Proceedings, 1648.

Mahdi, I., & Soliman, E. (2021). Significant and top ranked delay factors in Arabic Gulf countries. International Journal of Construction Management, 21(2), 167–180.

Manoharan, K., Dissanayake, P., Pathirana, C., Deegahawature, D., & Silva, R. (2025). Assessing the construction site supervisory attributes in effectuating mathematical theories and applications to construction operations. International Journal of Industrial Engineering and Operations Management, 7(3), 205-223.

Marović, I., Perić, M., & Hanak, T. (2021). A multi‐criteria decision support concept for selecting the optimal contractor. Applied Sciences (Switzerland), 11(4), 1–18.

Marzouk, M. M., El Kherbawy, A. A., & Khalifa, M. (2013). Factors influencing sub-contractors selection in construction projects. HBRC Journal, 9(2), 150–158.

Mazzoleni, M., & Paredi, D. (2022). Preliminary effects on the political accountability of the new accounting system for Italian local authorities. Corporate Ownership and Control, 19(2), 38–45.

Muneer, M., Khan, N., Awais Hussain, M., Shuai, Z., Khan, A. A., Farooq, R., ... & Tariq, M. A. U. R. (2022). A quantitative study of the impact of organizational culture, communication management, and clarity in project scope on constructions’ project success with moderating role of project manager’s competencies to enhance constructions management practices. Buildings, 12(11), 1856.

Nikmatul, K. A., Yudoko, G., & Firman, A. F. (2023). Improvement of turnaround maintenance project execution through long-term specific contracting strategy (A Case Study: Gas Processing Plant in Indonesia). European Journal of Business and Management Research, 8(4), 202–208.

Omran, A., Saleh, M. S. H., & Gebril, A. O. (2023). Factors Causing time and cost overruns of construction projects in Malaysia. Design, Construction, Maintenance, 3, 179–186.

Osati, M., & Omidvari, M. (2016). Performance measurement of electricity suppliers using PROMETHEE and balance scorecard. Management Science Letters, 387–394.

Polat, G., & Bingol, B. N. (2017). Data envelopment analysis (DEA) approach for making the bid/no bid decision: A case study in a Turkish construction contracting company. Scientia Iranica, 24(2), 497-511.

Polat, G., Eray, E., & Bingol, B. N. (2017). An integrated fuzzy MCGDM approach for supplier selection problem. Journal of Civil Engineering and Management, 23(7), 926–942.

Radziszewska-Zielina, E. (2016). The application of multi-criteria analysis in the evaluation of partnering relations and the selection of a construction company for the purposes of cooperation. Archives of Civil Engineering, 62(2), 167-182.

Rahadi, K. B., Setyanto, A., & Rohmansyah, D. (2021). Application of Theory of Constraints (TOC) in power generation to increase overhaul maintenance performance and to strengthen overhaul management process. IOP Conference Series: Materials Science and Engineering, 1096(1), 012130.

Rahimi, Y., Tavakkoli-Moghaddam, R., Shojaie, S., & Cheraghi, I. (2017). Design of an innovative construction model for supply chain management by measuring agility and cost of quality: An empirical study. Scientia Iranica, 24(5), 2515–2526.

Salehi, M. (2022). Global water shortage and potable water safety; Today’s concern and tomorrow’s crisis. Environment International, 158, 106936.

Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526.

Sanni-Anibire, M. O., Mohamad Zin, R., & Olatunji, S. O. (2022). Causes of delay in the global construction industry: a meta analytical review. International Journal of Construction Management, 22(8), 1395–1407.

Sarawa, D. I., & Mas' ud, A. (2020). Strategic public procurement regulatory compliance model with mediating effect of ethical behavior. Heliyon, 6(1), e03132.

Sayankar, V. N. (2015). A review on Theory of Constraints (TOC) in manufacturing. ZENITH International Journal of Business Economics & Management Research, 5(10), 34-41.

Shahvand, E., Sebt, M. H., & Banki, M. T. (2016). Developing fuzzy expert system for supplier and subcontractor evaluation in construction industry. Scientia Iranica. Transaction A, Civil Engineering, 23(3), 842.

Sharma, A., & Batra, R. K. (2016). Application of the analytical hierarchy process (AHP) in the selection of contractors/consultants. International Journal of Current Engineering and Scientific Research, 3(1), 128–134.

Shehu, Z., Endut, I. R., Akintoye, A., & Holt, G. D. (2014). Cost Overrun in The Malaysian construction industry projects: a deeper insight. International Journal of Project Management, 32(8), 1471–1480.

Siggelkow, N. (2007). Persuasion with case studies. Academy of Management Journal, 50(1), 20-24.

Tafesse, S. (2021). A review on the critical factors causing delay of delivery time in construction projects. International Journal of Engineering Technologies IJET, 6(4), 69-81.

Tong, L., Pu, Z., & Ma, J. (2019). Maintenance supplier evaluation and selection for safe and sustainable production in the chemical industry: A case study. Sustainability, 11(6), 1533.

Trinkūnienė, E., Podvezko, V., Zavadskas, E. K., Jokšienė, I., Vinogradova, I., & Trinkūnas, V. (2017). Evaluation of quality assurance in contractor contracts by multi-attribute decision-making methods. Economic Research-Ekonomska Istrazivanja, 30(1), 1152–1180.

Trojanowska, J., & Dostatni, E. (2017). Application of the theory of constraints for project management. Management and Production Engineering Review, 8(3), 87–95.

Unegbu, H. C. O., Yawas, D. S., & Dan Asabe, B. (2022). An investigation of the relationship between project performance measures and project management practices of construction projects for the construction industry in Nigeria. Journal of King Saud University – Engineering Sciences, 34(4), 240–249.

U-Sayee, C. R., & Adomako, E. B. (2021). Supervisory practices and challenges faced by senior high school principals in Greater Monrovia, Liberia: implications for quality education. Heliyon, 7(4), e06895.

Wahyudhi, R. T. (2021). Improving knowledge re use to reduce rework events in plant turnaround projects (Master’s thesis, Delft University of Technology). TU Delft Repository.

Walraven, A., & de Vries, B. (2009). From demand driven contractor selection towards value driven contractor selection. Construction Management and Economics, 27(6), 597–604.

Xie, Z., Tian, G., & Tao, Y. (2022). A multi-criteria decision-making framework for sustainable supplier selection in the circular economy and Industry 4.0 era. Sustainability, 14(24), 16809.

Yap, J. B. H., Goay, P. L., Woon, Y. B., & Skitmore, M. (2021). Revisiting critical delay factors for construction: Analysing projects in Malaysia. Alexandria Engineering Journal, 60(1), 1717–1729.

Yazdani, M., Wen, Z., Liao, H., Banaitis, A., & Turskis, Z. (2019). A grey combined compromise solution (CoCoSo-G) method for supplier selection in construction management. Journal of Civil Engineering and Management, 25(8), 858–874.

Yoon, J. H., & Pishdad-Bozorgi, P. (2022). Game theory-based framework for analyzing the collaborative dynamic of tacit knowledge sharing and the choice of procurement and contract types in mega construction projects. Buildings, 12(3), 305.

Young, J., & Osmani, M. (2013). Investigation into contractors’ responsible sourcing implementation practice. Proceedings of the Institution of Civil Engineers: Engineering Sustainability, 166(6), 320–329.

Zhang, X., & Wang, T. (2021). Understanding purchase intention in O2O E-Commerce: The effects of trust transfer and online contents. Journal of Theoretical and Applied Electronic Commerce Research, 16(2), 101–115.

Downloads

Published

2025-12-30

How to Cite

Alias, M. A., & Mohamad, F. (2025). Fostering transparency: Improvement of contractor selection criteria and practices. Journal of Governance and Integrity, 8(2), 1129-1139. https://doi.org/10.15282/jgi.8.2.2025.11519